Dredging and Disposal Project

Dredging

Dredging improves the efficiency of deep draft commercial navigation and reduces contaminated sediment from washing into Lake Michigan.

Note: In July 2021, USACE began the Phase 2 dike project to expand the CDF exterior dikes by 11 feet to maintain sufficient storage capacity for the intended project life, consistent with the original project authorization and plan. Dredging is not being performed while construction is underway. As a result, PID monitoring and turbidity monitoring are on hold. Real-time air monitoring continues in temporary locations off dike at onsite northeast and southeast stations using the M1 and M2 monitors (AM1 and AM2). The M3 and M4 monitors are not operating during dike expansion. Ambient air monitoring continues in one southwest location off dike (CON-SOUTH) and at the school. Dredging activities are anticipated to resume in 2024. More information »

Each year more than 100,000 cubic yards (CY) of contaminated sediment washes into the lake, including approximately 67,000 pounds of chromium, 100,000 pounds of lead, and 420 pounds of polychlorinated biphenyls (PCBs).

The Indiana Harbor and Canal (IHC) was not dredged from 1972 to 2012 due to a lack of suitable storage area for the contaminated sediments. The Confined Disposal Facility (CDF) was constructed to provide storage for the sediments. Dredging began in 2012 after the completion of the CDF to remove sediment that accumulated between 1972 and 2012, designated the “backlog sediment”. The completed backlog dredging produced approximately 1.7 million CY of dredged materials.

In July 2021, USACE began the Phase 2 dike project to expand the CDF exterior dikes by 11 feet to maintain sufficient storage capacity for the intended project life, consistent with the original project authorization and plan. After the dike raise, maintenance dredging will take place as required to remove re-accumulated sediments and maintain navigable depths in the harbor and canal.

What is Dredging?

Dredging is performed using a closed bucket (or clamshell bucket) mechanical dredge. The bucket scoops up sediment from the bottom of the waterway and loads it onto a barge for transport to the CDF.


The CDF operates as a "ponded" facility, which means the sediment is mixed with water to reduce the risk of potential air emissions. As the dredged material is unloaded from the barge, it is mixed with water from the CDF to make a mud mixture called a “slurry”. This slurry is then pumped into the CDF cells in a process called hydraulic off-loading. As the sediment settles to the bottom, the water that remains at the surface is then recycled and used for additional sediment placement. Air monitoring is conducted to ensure the safety of staff and the community.

Various dredging and placement alternatives were considered in an economic and environmental analysis performed by the USACE Engineer Research and Development Center. This approach was the least costly of those considered and has minimal environmental impacts.


Dredging Volume

The chart below shows a summary of dredging volume to present. Dredging is not expected from 2021 to 2024 due to dike expansion construction.

Bar chart showing the dredging volume in cubic yards from 2012 to 2020. Table provides data for this chart.
Year Volume (Cubic Yards)
2012 93,937
2013 305,947
2014 210,099
2015 318,202
2016 226,821
2017 94,054
2018 162,592
2019 167,845
2020 125,689

Thumbnail of map. Link is a PDF version of a detailed map and table.Map showing dredging amounts (December 2023)

Dredging Schedule

Dredging is on currently on hold due to dike expansion construction. During dredging, the typical work schedule is 24 hours a day, six or seven days a week. Each day consists of two 12-hour shifts.

  • Working at night reduces the effects of bridge openings on local traffic
  • Approximately half of all bridge openings will occur at night
  • Keeping the dredge barge constantly staffed prevents the need to move on- and off-station each day
  • This increases the work-time versus move-time ratio, increasing the productivity of each crew

See Traffic and Bridge Operations for details on detours and operations.

Dredging Areas

The map below shows the dredging areas in the Indiana Harbor and Canal, as well as the location of the CDF.

map
Map showing locations of dredging areas and the CDF [Source: USACE]

Notice to Mariners

Note: In July 2021, USACE began the Phase 2 dike project to expand the CDF exterior dikes by 11 feet to maintain sufficient storage capacity for the intended project life, consistent with the original project authorization and plan. Dredging is not being performed while construction is underway. As a result, PID monitoring and turbidity monitoring are on hold. Real-time air monitoring continues in temporary locations off dike at onsite northeast and southeast stations using the M1 and M2 monitors (AM1 and AM2). The M3 and M4 monitors are not operating during dike expansion. Ambient air monitoring continues in one southwest location off dike (CON-SOUTH) and at the school. Dredging activities are anticipated to resume in 2024. More information »