Skip to main content
Indiana Harbor and Canal
Dredging and Disposal Project

Confined Disposal Facility (CDF)

The Confined Disposal Facility (CDF) was constructed in stages from 2002–2011 to store the contaminated sediment from the Indiana Harbor and Canal (IHC) that is removed by dredging.

aerial photo
Aerial photograph of the CDF in 2015 [Source: USACE]

The CDF was designed to safely contain contaminated dredged sediments from the Indiana Harbor and Canal (IHC) onsite. It is located on a USEPA Resource Conservation and Recovery Act (RCRA) site in East Chicago, Indiana, on the Lake George Branch of the IHC. See the CDF Site History page for more information about the former refinery site on which the CDF was built.

Dikes of impervious clay material contain the dredged sediments. The center dike separates two “cells”, sometimes referred to as the “east cell” and the “west cell”.

A water treatment plant at the CDF treats sediment water, groundwater, and precipitation that accumulates in the CDF before it is discharged back to the Lake George branch of the canal. Three components work together to maintain an inward gradient to prevent groundwater from flowing away from the CDF site: a gradient control system, a groundwater cutoff wall, and a sealed sheet pile cutoff wall.

Legacy Issues and CDF Measures

The following table lists some issues encountered on the former refinery site, and the measures taken to address them at the CDF.

Legacy Issue

Measures Taken

Free product on groundwater (e.g., oil)
  • Groundwater cutoff walls
  • Gradient control system
Extensive soil contamination
  • Perimeter cover on the CDF site
  • Future clay closure cap
Buried waste and debris left on former refinery site
  • No digging in center of site
  • No waste removal
Poor groundwater and surface water quality
  • Onsite water treatment plant
Poor regional air quality
  • Air monitoring and emissions controls

CDF Features

diagram
Diagram showing east-west cross-section of the IHC CDF site. Extraction wells draw down the aquifer within the slurry and south cutoff wall to produce an inward hydraulic gradient, thereby preventing outward advective groundwater flow. [Source: USACE]

Slurry cutoff wall trenching during CDF construction [Source: USACE]

Slurry cutoff wall

The slurry cutoff wall is an underground clay wall approximately 40 feet deep around the perimeter of the CDF on the north, east, and west sides. Made of a soil bentonite slurry, it hydraulically isolates the groundwater at the site from the rest of the Calumet aquifer.


Completion of the construction of the sealed sheet pile cutoff wall [Source: USACE]

Sealed Sheet Pile Cutoff Wall

A sealed sheet pile cutoff wall at the canal on the south side of the site hydraulically isolates the groundwater at the site from the Lake George Branch of the IHC.


Clay dike construction [Source: USACE]

Clay dikes

Approximately 31-ft tall clay dikes hold the dredged material, and a 14-16 foot high center dike separates the CDF into two cells. The exterior dikes were raised by 11 feet between 2021 and 2024 to accommodate more dredged material. The center dike will be abandoned in the future after additional dredged material and water are added and the center dike is overtopped.


CDF east cell decant structure [Source: USACE]

Decant structures

Two decant structures in the CDF (one in each cell) can be used to control the water levels in the CDF. The decant structures can also be used minimize suspended solids in water to be pumped to the onsite treatment plant. The east cell decant structure was raised during the exterior dike expansion. The west cell decant structure was not expanded and can remain in use until the center dike is overtopped.


Extraction well installation [Source: USACE]

Gradient control system

The gradient control system pumps groundwater from the CDF to the CDF east cell and eventually to an onsite water treatment plant. The system consists of 96 vertical extraction wells that help to prevent offsite migration of contaminated groundwater from the former refinery site.


Water treatment plant [Source: USACE]

Water treatment plant

The water from the CDF is a combination of groundwater, dredge water, and precipitation. The water treatment plant treats water from the CDF cells to levels permitted for discharge back into the canal.


Other supporting features

Dredging off-load facilities, an administration building and parking lot, security features, storage facilities, decontamination pads (stations), and other support features have been constructed as necessary.

Administration building, parking lot, and storage facilities [Source: USACE]
A decontamination pad where vehicles are cleaned. The resulting sediment and water are collected for treatment. [Source: USACE]

RCRA

The CDF is a Resource Conservation and Recovery Act (RCRA) facility. The site requires RCRA corrective action due to the contamination of soil and groundwater on site from past industrial activities.

The CDF site currently has open RCRA status because the court-approved closure of the facility was not comparable to a RCRA-approved closure. The CDF design incorporates the “corrective action” for the pollutants left on the former ECI site. The gradient control system and cutoff walls are intended to meet the permeability requirements of 10-7 cm/s for the CDF perimeter.

Site Closure

The total capacity of the IHC CDF is 4.8 million cubic yards. The extension of the perimeter dikes completed in 2024 is designed to provide adequate sediment storage capacity for the design life. The facility will undergo RCRA closure after it no longer accepts dredged material. RCRA closure will include final clay cap (RCRA cap) that will maximize surface runoff from precipitation and minimize the amount of infiltration and percolation of water into the CDF. The final cap design will meet the regulatory requirements at the time of site closure.


Additional photos of the CDF are available for viewing in the Photo Gallery. Learn about the CDF construction history.