Indiana Harbor and Canal Confined Disposal Facility (IHC CDF) construction, dredging, and facility operation timeline.
Milestone | Date | Description |
---|---|---|
IHC Comprehensive Management Plan (CMP) | January 1999 | Included a Feasibility Report and Environmental Impact Statement that described conceptual design of the CDF and was used as the basis for incremental regulatory approval. |
IHC Maintenance and Dredging Design Documentation Report | March 2000 | Outlined preliminary design of CDF to support federal cost estimate and project partnership agreement. |
Air Monitoring | Ongoing (started 2001) | Monitoring of atmospheric conditions at the CDF and East Chicago High School for CDF chemicals of concern to evaluate the effect of CDF operations on surrounding community. |
Subsurface Investigation and Cutoff Slurry Wall Construction | 2002 - 2004 | Installation of soil-bentonite slurry wall along west, north, and east sides, and keyed into the clay layer below. |
CDF Dike Construction | 2004 - 2010 | Installation of clay dikes to contain dredged material. Construction took place in three phases based on availability of funds and real estate consideration. |
South Cutoff Wall Construction | 2007 - 2009 | Installation of approximately 2,000 linear feet of sealed sheet pile wall along the canal and keyed into the slurry wall and clay layer. |
Interim Wastewater Treatment Plant Operation | 2007 - 2012 | On-site groundwater treatment and off-site discharge. Groundwater extracted from temporary well points, treated, and discharged to Lake George Branch. |
Gradient Control System (GCS) Construction | 2007 - 2012 | Installation of 88 groundwater extraction wells, 42 monitoring wells, 2 ultrasonic sensors, and associated components for groundwater control at the site. Final calibration was conducted during the Performance Calibration Test in April, 2012. |
CDF South End Feature Construction | 2010 - 2012 | Construction of CDF support facilities and infrastructure including administrative building, storage facilities, access roads. |
Dredging and Facility Operations | Ongoing (started 2012) | Contract includes dredging and offloading operations as well as operation of the GCS and wastewater treatment plant. |
Additional Extraction Wells Construction | 2015 | Installation of eight additional extraction wells to GCS. |
Phase 2 Dike Project | 2021-2024 | Expansion of the CDF exterior dikes began in July 2021. Construction was completed in June 2024. |