Skip to main content
Indiana Harbor and Canal
Dredging and Disposal Project
Return to Reports

Air Monitoring Alarm Response

Air Monitoring Instrument
Thermo Scientific Model 5030 Sharp Monitor
Date and time of alarm
10/7/2024 4:30 PM
to
4:30 PM
Air monitoring station
checked
M2
Alarm was caused by
checked
Air quality, traffic, site maintenance, insects
Name of technician who responded to the alarm
Scott Peterson
Was an email sent to the site technician?
checked
Yes
Were dredging or construction occurring during the alarm?
checked
Yes
Was dredging suspended?
checked
No
Were corrective actions taken?
checked
No
Description of action taken
Driving too fast on the upper gravel ring road.